Spirit - Raising the level in housing standards
 
Tees Valley Housing Group
Recent developments

The Gates, York

Richmond Street – 59 completed (21 for York Housing Association). The remaining 26 are due to complete in October 2011.

Regent Street – 9 completions. 49 remaining and due to complete in September 2012.

Auden House, York

41 unit Extra Care scheme build for York Housing Assocation completed in January 2011.
Woodland View, Darlington

8 completions so far with 98 remaining. Final completions due March 2012.
York Revival Phase 2

10 completions so far with a further 6 due in December 2011
Nursery Gardens, Stockton
Completed in September 2011

12 units
Heworth Green
Completed in June 2011

33 units
Prospect Farm, Easingwold
Completed in December 2010

21 units
Trinity Gardens, North Ormesby
Completed in September 2010

53 units
Trinity Phase 1
North Ormesby, Middlesbrough

9 units
Prospect Farm
Easingwold
7 units
Discus
Richmond Street, York

15 units (8 for TVHL and, 7 for YHA)
Bowesfield Lane
Stockton
12 units
Trinity Phase 5

5 units
Discus
St. Ann's Court, York
12 units for YHA
York Revival

7 units
Stafford Villa
Thornaby
8 supported units
Hawkshead Place
Newton Aycliffe
88 units
Whinney Banks Phase 2b
Middlesborough
8 units
Whinney Banks Phase 2d
Middlesborough
7 units
Chapelfields Road
York
9 units
Staiths
Gateshead
8 units
Whinney Banks Phase 3a1
Middlesborough
8 units
Church Lane
Eston
26 units
The Courts Phase 3

34 units
Trinity Phase 4

4 units
 
 
Three Rivers
Tees Valley
  Recent Developments
  Upcoming Developments
Two Castles
Coast & Country
Erimus
Housing Hartlepool
Sedgefield Borough Housing
 
 
 
       
  Three Rivers Housing GroupTees Valley Housing GroupTwo Castle Housing AssociationCoast & Country HousingErimus HousingHousing HartlepoolSedgefield Borough Homes Broadacres Housing Assocation South Tyneside Homes